05-08-2022, 04:48 AM
Hi,
I think I found something else :
When setting the same initial date for 2 different tasks and setting :
Task 1 : only Friday, every 4 week
Task 2 : every day except sat, sun, every 4 week
Then it run once for both task but after running task 1 new scheduled date os correct (in 4 week) however for task 2 it is not correct, new scheduled date is in 3 weeks and I need to set 5weeks as a parameter and then it’s scheduled in 4 week.
Can you help with this one too ?
I think I found something else :
When setting the same initial date for 2 different tasks and setting :
Task 1 : only Friday, every 4 week
Task 2 : every day except sat, sun, every 4 week
Then it run once for both task but after running task 1 new scheduled date os correct (in 4 week) however for task 2 it is not correct, new scheduled date is in 3 weeks and I need to set 5weeks as a parameter and then it’s scheduled in 4 week.
Can you help with this one too ?